Following a feasibility study, The QS Company undertook a value engineering exercise, focusing on key cost drivers such as:
Functional areas/amenity space, Considerations for a sloping site, Basement, Wall:floor ratio, Net:Gross Ratio, Façade materials, Adjacent high street access, Dense unit mix
5 Cost plan and design reiterations were undertaken, increasing the number of units from 120 to 150 and reducing cost by around £1.6m.